"ALBUQUERQUE, N.M. — A federal judge is being asked to issue a stop-work order on a $10 billion transmission line being built through a remote southeastern Arizona valley to carry wind-generated electricity to customers as far away as California.
A 32-page lawsuit filed on Jan. 17 in U.S. District Court in Tucson, Arizona, accuses the U.S. Interior Department and Bureau of Land Management of refusing for nearly 15 years to recognize “overwhelming evidence of the cultural significance” of the remote San Pedro Valley to Native American tribes including the Tohono O’odham, Hopi, Zuni and San Carlos Apache Tribe.
The suit was filed shortly after Pattern Energy received approval to transmit electricity generated by its SunZia wind farm in central New Mexico through the San Pedro Valley east of Tucson and north of Interstate 10."
Susan Montoya Bryan and Ken Ritter report for the Associated Press January 23, 2024.